The track record with our Gyro steering tool and add-on modules spans in excess of 20,000 completed drills. Each project has its own story and its own hurdles that needed to be negotiated. Our reliable and unique service offering was a big driver in the completion of each of these projects. 

Category
Challenging HDD intersect to cross wetlands near Surrey, BC

In September 2023, Brownline Canada made a major contribution to a pipeline project in British Columbia. In a wetlands...

Read more
World record length for 42” HDPE force main under James River, VA

In February 2024, Brownline USA made a key contribution to the installation of a force main under James River, Virginia....

Read more
Surveying 7 HDD crossings in Zeeland

The Deltaweg (N256) is one of the busiest roads in Zeeland and is an important traffic artery for passenger and freight...

Read more
Four HDD crossings for undergrounding of 150 kV lines

In September 2023, Brownline contributed to four directional drillings in Breda. Here, an overhead powerline above the...

Read more
Very long HDD outfall into the North Sea

In January 2023, Brownline contributed to a special project: installing an optic fibre connection between the United Kingdom...

Read more
Long parallel crossings under many obstacles in Rijswijk

In June 2023, Brownline contributed to the completion of two parallel crossings in Rijswijk. To install heat pipelines,...